Types of bill of quantities
Contents |
[edit] Introduction
A bill of quantities (sometimes referred to as a 'BoQ' or 'BQ') is a document, typically prepared by a cost consultant (often a quantity surveyor) that provides measured quantities of the items of work identified by the drawings and specifications in the tender documentation for a project. It is issued to tenderers for them to prepare a price for carrying out the works.
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are two types of bill of quantities; firm and approximate.
[edit] Firm bill of quantities
A firm bill of quantities is used to obtain a lump-sum price for a fully-designed project. The work required is measured and described precisely, meaning that it can be priced accurately. As a result, tender prices should be reliable and good financial control should be possible. Where changes are necessary to the works described in the tender documents, the bill of quantities provides a good basis for assessing the costs of those changes.
[edit] Approximate bill of quantities
An approximate bill of quantities (sometimes referred to as a notional bill of quantities or provisional bill of quantities) is subject to re-measurement, and is used if there is insufficient information to prepare a firm bill of quantities at the tender stage, or if it is decided that a firm bill of quantities is not necessary.
The description of the works required is complete, but the quantities are approximate. As a result, quantified schedule of rates are provided by tenders rather than a lump-sum price, and the quantities are subject to re-measurement on completion.
This may appear an attractive option, as less cost and time is required to prepare the bill of quantities, however, typically, there will be more variations, and as re-measurement is required, overall administrative costs may be higher. In addition, there is greater cost uncertainty.
See also: Bill of quantities breakdown structures for descriptions of the three main breakdown structures for bills of quantities:
NB: An 'unpriced bill of quantities' (sometimes referred to as the tender pricing document) is the document issued to tenderers, who will then estimate their price for each item. The 'priced bill of quantities' constitutes the tenderer's offer and is the unpriced bill of quantities, but with the tenderer’s rates, costs and totals added.
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Approximate quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- New Rules of Measurement.
- NRM1.
- NRM2.
- NRM3.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Without quantities.
- Work package bill of quantities.
- Work section bill of quantities.
Featured articles and news
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.